Tata Electronics in Dholera
The anchor investor and its fab
| Company | Tata Electronics (Tata Group) |
|---|---|
| Project | Rs 91,000 crore semiconductor fab |
| Partner | PSMC, Taiwan |
| Approved | Union Cabinet, 29 February 2024 |
| Capacity | up to 50,000 wafers/month, 300mm |
Tata Electronics is the anchor investor whose semiconductor fab gives Dholera its single most important, physically-under-construction reason to exist as an industrial city.
The company and the project
The anchor industrial investment is the Tata Electronics semiconductor fab, approved by the Union Cabinet on 29 February 2024 under the India Semiconductor Mission, a Rs 91,000 crore facility built with Taiwan's PSMC for up to 50,000 wafers a month on a 300mm line. Tata Electronics is the Tata Group's electronics-manufacturing arm, and its Dholera fab is being built with Taiwan's Powerchip Semiconductor Manufacturing Corporation (PSMC) as technology partner. Cabinet approval came on 29 February 2024 under the India Semiconductor Mission. Confirmed
Why one investor matters this much
A greenfield industrial region lives or dies on anchor tenants, and a fab of this scale pulls in suppliers, utilities demand, skilled jobs and housing pressure around it. That is why Dholera's credibility rose sharply once the fab moved from announcement to construction. The counterweight to keep in mind is concentration risk: much of the near-term story rests on this one project executing on schedule. First mature-node output is a stated target, not yet an achievement. Reported
This article follows Dholerapedia's sourcing standard: every figure is tagged Confirmed (government or official), Reported (press or trade) or Unverified (broker), and dated. Anything framed as a future event is labelled a target until a government source confirms it. Where a fact is not reliably available, we say so rather than estimate. See the methodology.
Key facts
The core facts for tata electronics in dholera are summarised below; each is drawn from the sources listed at the foot of this article and dated to the review month.
- Company: Tata Electronics (Tata Group).
- Project: Rs 91,000 crore semiconductor fab.
- Partner: PSMC, Taiwan.
- Approved: Union Cabinet, 29 February 2024.
- Capacity: up to 50,000 wafers/month, 300mm.
Context
Dholera SIR is planned over about 920 sq km, of which roughly 422 sq km is designated for urban development across six town-planning schemes phased over about three decades. It is governed by the DSIRDA (planning authority) and built by DICDL, a special purpose vehicle held 51% by Gujarat and 49% by the central government through the NICDC Trust, and it is the flagship node of the Delhi-Mumbai Industrial Corridor. This context frames every article on the region; the specifics of this topic are covered above, and the full picture is in What is Dholera SIR and the master plan.
Reading this reference
Dholerapedia is a reference, so it is built to be checked rather than believed. Every figure in this article is tagged by source, Confirmed for a government or official record, Reported for press or trade coverage, and Unverified for a broker claim, and each carries a date because Dholera changes and a number that was right last year may not hold now. Anything described as a future event is treated as a target until a government source confirms it, and where a fact is not reliably available the article says so instead of guessing. None of this is investment, legal or tax advice, and no government source guarantees appreciation. If you are evaluating a specific plot, the figures here are context, not a substitute for confirming that parcel's GUJRERA registration, title and price yourself. Corrections that improve accuracy are welcome via the contact page, and entries are updated as official figures change rather than left stale. The reason for this standard is simple: a reference is only worth reading if you can act on it and check it, so we would rather show a smaller number of well-sourced facts than a larger number of impressive-sounding ones. Where a claim about Dholera circulates widely but rests only on a broker source, we note it as unverified rather than repeat it as settled, and where the official record and the marketing disagree, we follow the official record. For the collected figures across the encyclopedia, see Dholera in numbers, and for the full method see the methodology.
References
- Press Information Bureau, Union Cabinet approval, 29 February 2024 (India Semiconductor Mission).
- NICDC Delivery Monitoring Unit report, 30 June 2026 (DPIIT).